Projectname |
Client |
Contract Value(MB) |
Completion
Date |
Scope Of Work |
WASTE WATER COLLECTION PIPING AT BANGPOO INDUSTRIAL ESTATE |
GLOBAL ENVIRON MENTAL TECHNOLOGY CO., LTD. |
23.1 |
15 OCT 2003 |
CONSTRUCTION FOR WASTE WATER COLLECTION PIPING AT BANGPOO INDUSTRIAL ESTATE |
WASTEWATER TREATMENT PLANT FOR BANGPOO INDUSTRIAL |
GLOBAL ENVIRONMENTAL TECHNOLOGY CO., LTD. |
95.3 |
31 JUL 2001 |
ENGINEERING, PROCUREMENT AND CONSTRUCTION FOR WASTEWATER TREATMENT PLANT (MECHANICAL, ELECTRICAL CONTROL AND INSTRUMENT) 35,000 CUM/DAY |
RATCHABURI-SAMUTSONGKRAM WATER PIPE LINES |
ESCO |
40.4 |
15 NOV 2000 |
SUPPLY & INSTALLATION OF CITY WATER WORK TRANSMISSION PIPE LINE ALONG THE PUBLIC ROADS |
RATCHBURI-SAMUTHSONGKRAM WATER PIPE LINE B |
ESCO |
7.4 |
31 JUL 2000 |
CONSTRUCTION MANAGEMENT FOR CITY WATER WORK TRANSMISSION PIPE LINE |
RATCHBURI-SAMUTHSONGKRAM WATER PIPE LINE A |
EGCO ENGINEERING & SERVICE CO., LTD.( ESCO ) |
31.9 |
31 MAR2000 |
SUPPLY & INSTALLATION OF CITY WATER WORK TRANSMISSION PIPE LINE ALONG THE PUBLIC ROADS |
WASTE WATER TREATMENT PLANT FOR ASIAN GAMES 13th - 7 GYMNASIUM BUILDINGS - THAMMAST UNIVERSITY RANGSIT CAMPUS |
MINISTRY OF FINANCIAL |
23.0 |
31 DEC 1998 |
SUPPLY AND INSTALLATION FOR WASTE WATER TREATMENT PLANT FOR 7 GYMNASIUM BUILDINGS OF SPORT COMPLEX - TOTAL CAPACITY 1,000 CUM./DAY |
WASTE WATER TREATMENT PLANT FOR ATHLETE VILLAGE ( 5000 UNITS) FOR ASIAN GAMES 13th - THAMMASAT UNIVERSITY RANGSIT CAMPUS |
MINISTRY OF FINANCIAL |
25.0 |
31 DEC 1998 |
SUPPLY AND INSTALLATION FOR WASTE WATER TREATMENT PLANT FOR 5,000 UNITS OF ATHELETE VILAGES ( EXTENDED AERATION ACTIVATED SLUDGE ) - TOTAL CAPACITY 1,500 CUM./DAY |
INFRASTRUCTURE PHASE 1 FOR ASIAN GAMES 13th -THAMMAST UNIVERSITY SPORT COMPLEX (RANGSIT CAMPUS) |
MINISTRY OF FINANCE |
53.9 |
30 JUN 1997 |
SUPPLY AND INSTALLATION OF WATER TREATMENT PLANT - CAPACITY 4,800 CUM./DAY AND WASTE WATER TREATMENT PLANT- CAPACITY 12,960 CUM./DAY WITH ELECTRICAL POWER SUPPLY AND CONTROL SYSTEM |
BACK WASH SYSTEM FILTER HOUSE 1,2,3,4 |
METROPOLITAN WATER WORK AUTHORITY |
5.8 |
25 OCT 1995 |
IMPROVE BACK WASH SYSTEM |
SAMSEN - NAKHONCHAISRI WATER SUPPLY PLANT SAWANKALOK ROUTE |
METROPOLITAN WATER WORK AUTHORITY |
15.7 |
7 JUL 1994 |
IMPROVE PLUMBING & ACCESSORIES AND SANITARY SYSTEMS |