Projectname |
Client |
Contract Value(MB) |
Completion
Date |
Scope Of Work |
STEAM DISTRIBUTION SYSTEM FOR TLP COGENERATION |
TPL COGENERATION CO., LTD. |
14.7 |
25 DEC 2003 |
DESIGN, SUPPLY, CONSTRUCTION, ERECTION, TEST & COMMISSIONING OF STEAM DISTRIBUTION SYSTEM AND CONDENSATE RETURN SYSTEM FROM TLP COGEN. TO TUNTEX TEXTILE FACTORY (CIVIL, MECHANICAL, ELECTRICAL, CONTROL AND INSTRUMENT) |
CIRCULATING WATER MAKEUP SYSTEM FOR KRABI THERMAL PLANT UNIT 1 |
EGAT |
170.8 |
21 OCT 2001 |
DESING, SUPPLY CONSTRUCTION, ERECTION, TEST AND COMMISSIONING OF MECHANICAL, ELECTRICAL, CONTROL AND INSTRUMENTATION FOR CIRCULATING WATER MAKE UP SYSTEM. THE SYSTEM CONSIST OF INTAKE STRUCTURE, 2 x 2,300 M3/HR CW MAKE UP PUMPS, DIA. 650 MMX 350 M. LO |
STORAGE TANK AND ACCESSORIES FOR KRABI THERMAL POWER PLANT |
EGAT |
61.3 |
31 JAN 2000 |
DESIGN, FABRICATION, SUPPLY, TRANSPORTATION AND SUPERVISION OF STORAGE TANK AND ACCESSOIRES SYSTEM. THE SYSTEM CONSIST OF 4 x 2,000 CUM WATER STORGE TANKS, 1 x 2,000 CUM FUEL OIL STORGE TANK, 2 x 10,000 CUM FUEL OIL STORGE TANK UNLOADING SYSTEM, FIRE PO |
HEAT RECOVERY STEAM GENERATOR BLOCK 1 (HRSG 1A &1B) RATCHABURI COMBINED CYCLE POWER PLANT |
EGAT |
39.0 |
11 JAN 1999 |
INSTALLATION & ERECTION OF HEAT RECOVERY STEAM GENERATOR BLOCK 1 (HRSG 1A &1B) |
STEAM DISTRIBUTION PIPING SYSTEM FOR AMATA-EGCO |
AMATA-EGCO POWER LIMITED |
40.5 |
1 JAN 1999 | SUPPLY AND ERECTION OF STEAM DISTRIBUTION PIPING SYSTEM FOR POWER PLANT |
HANDRIAL AND TOE PLATE FOR WANG NOI COMBINED CYCLE PLANT STAGE II |
MITSUBISHI CORPORATION |
1.7 |
1 JAN 1997 |
SUPPLY , FABRICATION AND TRANSPORTATION OF HANDRIAL ANDTOEPLATE FOR WANG NOI COMBINED CYCLE PLANT |
HANDRIAL & TOE PLATE FOR WANG NOI COMBINED CYCLE PLANT STAGE I |
MISUBISHI CORPORATION |
3.3 |
1 MAY 1996 |
SUPPLY AND FABRICATION OF HANDRAIL & TOE PLATE FOR WNCC I FOR BOILERS (80 TONS) |
OIL & WATER STORAGE TANK, NONG CHOK GAS TURBINE POWER PLANT |
EGAT |
52.1 |
1 SEP 1995 |
FABRICATION AND ERECTION OF 2 x OIL STORAGE TANK (10,200 M3), 3 x WTR STORAGE TANK (1,770 M3), INCLUDING PILING & FOUNDATION |
GENERAL M & E CONSTRUCTION SOUTH BANGKOK COMBINED CYCLE POWER PLANT BLOCK 1 (325 MW) |
EGAT | 563.4 |
1 AUG 1994 |
CONSTRUCTION & COMMISSIONING FOR 1 x STEAM TURBINE & GENERATOR, 2 x HRSG 2P 80 BAR, PLANT DCIS HV - LV ELECTRICAL, FURNISH & INSTALL ALL MECHANICAL, ELECTRICAL CABLES, RACEWAY & INSTRUMENTATION |
GENERAL M & E CONSTRUCTION RAYONG COMBINED CYCLE POWER PLANT BLOCK 4 (300 MW) |
EGAT |
510.0 |
1 JAN 1993 |
CONSTRUCTION & COMMISSIONING FOR 1 x STEAM TURBINE & GENERATOR, 2 x HRSG. 2P 80 BAR, PLANT DCIS HV-LV ELECTRICAL, FURNISH & INSTALL ALL MECHANICAL BOP, ELECTRICAL CABLES, RACEWAY & INSTRUMENTATION |